Local Property News | Posted by Hnin Ei Khin
A green light was given to Traffic for crossing over the Bayintnaung Bridge-1 according to the Ministry Of Construction (Roads and Bridges).
The Ministry Of Construction (Roads and Bridges) is now fixing the bridge’s bearing and expansion joints and it is now 75% complete.
It will be complete on 29 November.
The load testing of the bridge will be conducted on 30 November and then traffic will be allowed to cross over it. Starting from on 30 November afternoon, the green light will be given to traffic on their regular route. The load capacity of tons are the same as before.